Australian Aboriginal Mining Corporation

Australia’s first substantially Indigenous owned iron ore mine (Investment Decision September 2019)

Australian Aboriginal Mining Corporation

Australia’s first substantially Indigenous owned iron ore mine.

Sector: Resources.

NAIF loan Total project value
Up to $12.5m* $45.0m
Public Benefit Jobs
$304m Up to 120 jobs during construction, with a further 120 roles during operations.

About the Project

Australian Aboriginal Mining Corporation Limited (AAMC) will develop the First Iron Project, located in the Pilbara, 80km northwest of Newman.

AAMC is a substantially Aboriginal owned, operated and managed company, part-owned by Indigenous owned Carey Group Holdings that includes Indigenous contractor Carey Mining.

The deposit will be mined on a contract basis by Carey Mining, with two million tonnes of ore a year trucked 190km to Fortescue Metals Group’s Cloudbreak mine.

Infrastructure

NAIF’s Investment Decision will enable the construction of a borefield, crushing plant and site accommodation, and a 55km haul road to connect the Great Northern Highway to the Cloudbreak mine.

The Value NAIF Brings

NAIF’s loan enables the construction of the project, in partnership with a loan from a commercial financier. NAIF’s ability to provider longer tenor than commercial financiers, taking into account commodity price analysis, has been the catalyst in filling the funding gap for this project to proceed.

NAIF’s investment in the project demonstrates its support of Aboriginal ownership and Indigenous proponents, in the resources industry where Aboriginal economic participation has predominantly been through employment. The project could be a milestone for stronger Indigenous economic participation in the Pilbara resources sector.

Indigenous Engagement

Established in 2013, AAMC works to identify and promote opportunities for the development of Aboriginal mining capability and capacity in the Pilbara.

AAMC has committed to a range of activities under its Indigenous Engagement Strategy including the employment of an Aboriginal Liaison Officer, development of Aboriginal procurement targets and establishing culturally appropriate Aboriginal employment policies, training and mentoring programmes. Goods and services provided by local businesses will be matched with procurement opportunities and policies to attract and retain Aboriginal business will be implemented.

The creation of an Australian Aboriginal Mining Academy (AAMA) to provide education opportunities to local Aboriginal people is also being explored.

* The financial assistance is subject to conditions including the finalisation of the Western Australia Government’s consideration and agreement for the approved funds to be advanced.

Economic Impact and Public Benefit

  • Australia’s first substantially Indigenous owned iron mine.
  • Up to 120 jobs are forecast to be created during construction, with a further 120 roles during ongoing operations.
  • Independent analysis has forecast the net public benefit from the project to be $304m.

The NAIF media release on the Investment Decision to AAMC can be found here.